CPP Cheat Sheet 2026

The 30 highest-yield CPP facts, distilled from real exam questions. Print it, save it as a PDF, or study it here — free, no sign-up.

100 questions
90 min time limit
70.00% to pass
  1. A sponsor asks why the project budget includes amounts above the cost baseline. The project manager should explain that the difference represents what? Management reserve for unknown risks
  2. Which of the following situations would MOST likely trigger a constructive change to a contract? The buyer verbally directs the seller to perform out-of-scope work
  3. During a team retrospective, a team member blames another for a missed deadline in front of the group. What should the project manager do FIRST? Redirect the discussion toward identifying process improvements, not individuals
  4. When actual cost exceeds planned cost at a reporting period, what is the financial implication? The project is over budget for that period
  5. What is the purpose of a 'Scrum of Scrums' in a scaled Agile environment? To coordinate dependencies and impediments across multiple Scrum teams
  6. A project manager notices that two senior team members consistently disagree in meetings, slowing decision-making. What is the BEST first step? Meet with each member privately to understand their perspectives
  7. Which output of the Sequence Activities process is a graphical representation showing the logical order and dependencies among project activities? Project schedule network diagram
  8. A requirements attribute that describes how important a requirement is to a stakeholder relative to other requirements is called: Priority
  9. When should lessons learned sessions ideally be conducted on a large project? At key phase gates and project closure
  10. In EVM, the Performance Measurement Baseline (PMB) is typically represented by: The S-curve of cumulative Planned Value
  11. During integrated change control, who holds final authority to approve or reject changes on a large program? The Change Control Board (CCB)
  12. Portfolio balancing refers to the practice of: Optimizing the mix of projects across risk, time horizon, and strategic dimensions
  13. Which tool helps in planning stakeholder communication? Communication management plan
  14. A project manager is conducting a 'make-or-buy' analysis. The primary purpose of this analysis is to: Determine whether to produce a deliverable internally or procure it externally
  15. Which document formally authorizes a project and grants the project manager authority to apply organizational resources? Project Charter
  16. A project team is applying the Plan-Do-Check-Act (PDCA) cycle to improve a quality process. During the 'Check' phase, what is the primary activity? Analyzing results to determine if the change achieved the desired improvement
  17. What is the role of the project manager when a CCB decision conflicts with their professional judgment about a change? Escalate concerns through proper channels while complying with the CCB decision
  18. A CPP project manager wants to prioritize which risks to address first using limited resources. Which tool is most appropriate for this? Probability and impact matrix
  19. Configuration identification involves which of the following activities? Selecting and labeling configuration items and establishing baselines
  20. Which ANSI/EIA-748 guideline criterion requires that the project budget be time-phased? Criterion 9 (Budgeting)
  21. Which of the following is an example of an explicit organizational process asset related to lessons learned? A documented project post-mortem stored in a shared repository
  22. A project has BAC = $500,000, EV = $300,000, and AC = $350,000. What is the Cost Performance Index (CPI)? 0.86
  23. What challenge is most commonly encountered in lessons learned & knowledge management within Certified Project Professional practice? Resistance to change and difficulty maintaining consistency across stakeholders
  24. During a lessons learned session, a team member becomes defensive when their decisions are discussed. What facilitation approach is MOST effective? Focus on processes and systems rather than individuals
  25. A schedule baseline differs from the project schedule primarily because the baseline is: The approved version used for comparison and performance measurement
  26. Scope verification (Validate Scope) is primarily concerned with: Obtaining formal stakeholder acceptance of completed deliverables
  27. What is the purpose of quality assurance (QA)? To audit processes for compliance and effectiveness
  28. What is the purpose of releasing project resources during closeout? To make team members available for other organizational work
  29. How does procurement & contract management contribute to professional excellence in CPP certification? It enhances competency, improves outcomes, and supports continuous professional growth
  30. In Scrum, who is responsible for maximizing the value of the product and managing the Product Backlog? Product Owner
Turn these facts into recall:
Was this helpful?