CPP Cheat Sheet 2026
The 30 highest-yield CPP facts, distilled from real exam questions. Print it, save it as a PDF, or study it here — free, no sign-up.
100 questions
90 min time limit
70.00% to pass
- A sponsor asks why the project budget includes amounts above the cost baseline. The project manager should explain that the difference represents what? → Management reserve for unknown risks
- Which of the following situations would MOST likely trigger a constructive change to a contract? → The buyer verbally directs the seller to perform out-of-scope work
- During a team retrospective, a team member blames another for a missed deadline in front of the group. What should the project manager do FIRST? → Redirect the discussion toward identifying process improvements, not individuals
- When actual cost exceeds planned cost at a reporting period, what is the financial implication? → The project is over budget for that period
- What is the purpose of a 'Scrum of Scrums' in a scaled Agile environment? → To coordinate dependencies and impediments across multiple Scrum teams
- A project manager notices that two senior team members consistently disagree in meetings, slowing decision-making. What is the BEST first step? → Meet with each member privately to understand their perspectives
- Which output of the Sequence Activities process is a graphical representation showing the logical order and dependencies among project activities? → Project schedule network diagram
- A requirements attribute that describes how important a requirement is to a stakeholder relative to other requirements is called: → Priority
- When should lessons learned sessions ideally be conducted on a large project? → At key phase gates and project closure
- In EVM, the Performance Measurement Baseline (PMB) is typically represented by: → The S-curve of cumulative Planned Value
- During integrated change control, who holds final authority to approve or reject changes on a large program? → The Change Control Board (CCB)
- Portfolio balancing refers to the practice of: → Optimizing the mix of projects across risk, time horizon, and strategic dimensions
- Which tool helps in planning stakeholder communication? → Communication management plan
- A project manager is conducting a 'make-or-buy' analysis. The primary purpose of this analysis is to: → Determine whether to produce a deliverable internally or procure it externally
- Which document formally authorizes a project and grants the project manager authority to apply organizational resources? → Project Charter
- A project team is applying the Plan-Do-Check-Act (PDCA) cycle to improve a quality process. During the 'Check' phase, what is the primary activity? → Analyzing results to determine if the change achieved the desired improvement
- What is the role of the project manager when a CCB decision conflicts with their professional judgment about a change? → Escalate concerns through proper channels while complying with the CCB decision
- A CPP project manager wants to prioritize which risks to address first using limited resources. Which tool is most appropriate for this? → Probability and impact matrix
- Configuration identification involves which of the following activities? → Selecting and labeling configuration items and establishing baselines
- Which ANSI/EIA-748 guideline criterion requires that the project budget be time-phased? → Criterion 9 (Budgeting)
- Which of the following is an example of an explicit organizational process asset related to lessons learned? → A documented project post-mortem stored in a shared repository
- A project has BAC = $500,000, EV = $300,000, and AC = $350,000. What is the Cost Performance Index (CPI)? → 0.86
- What challenge is most commonly encountered in lessons learned & knowledge management within Certified Project Professional practice? → Resistance to change and difficulty maintaining consistency across stakeholders
- During a lessons learned session, a team member becomes defensive when their decisions are discussed. What facilitation approach is MOST effective? → Focus on processes and systems rather than individuals
- A schedule baseline differs from the project schedule primarily because the baseline is: → The approved version used for comparison and performance measurement
- Scope verification (Validate Scope) is primarily concerned with: → Obtaining formal stakeholder acceptance of completed deliverables
- What is the purpose of quality assurance (QA)? → To audit processes for compliance and effectiveness
- What is the purpose of releasing project resources during closeout? → To make team members available for other organizational work
- How does procurement & contract management contribute to professional excellence in CPP certification? → It enhances competency, improves outcomes, and supports continuous professional growth
- In Scrum, who is responsible for maximizing the value of the product and managing the Product Backlog? → Product Owner
Turn these facts into recall:
Was this helpful?