CPP CPP Project Closeout & Benefits Realization 1 — Questions and Answers
Question 1: Which document formally confirms that project deliverables have been accepted and the project is complete?
- Project Charter
- Scope Statement
- Project Closure Report (Correct answer)
- Lessons Learned Register
Correct answer: Project Closure Report
The Project Closure Report formally documents acceptance of deliverables and signifies project completion.
Question 2: Benefits realization management (BRM) is primarily concerned with ensuring that:
- The project finishes on schedule
- Planned benefits are actually achieved after project completion (Correct answer)
- Stakeholders approve the project charter
- The project budget is fully spent
Correct answer: Planned benefits are actually achieved after project completion
BRM focuses on tracking and confirming that the intended business benefits are delivered following project closure.
Question 3: What is the primary purpose of a post-implementation review (PIR)?
- To approve the project budget
- To assess whether project objectives and benefits were achieved (Correct answer)
- To kick off the next project phase
- To reassign team members to new projects
Correct answer: To assess whether project objectives and benefits were achieved
A PIR evaluates the outcomes of a completed project against its original objectives and expected benefits.
Question 4: During project closeout, which activity ensures that all contractual obligations with vendors have been fulfilled?
- Scope verification
- Contract closure (Correct answer)
- Risk response planning
- Quality auditing
Correct answer: Contract closure
Contract closure confirms that all deliverables have been received, invoices settled, and contractual terms satisfied.
Question 5: A benefits realization plan should be owned by:
- The project manager alone
- The project sponsor or business owner (Correct answer)
- The lead developer
- The PMO administrator
Correct answer: The project sponsor or business owner
The sponsor or business owner retains accountability for realizing benefits, which often continue after the project manager's role ends.
Question 6: Which of the following is a key output of the Close Project or Phase process in the PMBOK® Guide?
- Project charter
- Risk register
- Final product, service, or result transition (Correct answer)
- Work breakdown structure
Correct answer: Final product, service, or result transition
The Close Project or Phase process formally delivers the final product, service, or result to the customer or operations team.
Which document formally confirms that project deliverables have been accepted and the project is complete?