A project sponsor requests a major new feature after the project has passed the halfway mark. The project manager should FIRST:
-
A
Immediately begin implementing the feature
-
B
Reject the request since the project is past halfway
-
C
Assess the impact on scope, schedule, cost, and risk before deciding
-
D
Add the feature only if no additional resources are needed