A project manager identifies that the project schedule has a Schedule Performance Index (SPI) of 0.85. What does this indicate?
-
A
The project is 15% ahead of schedule
-
B
The project is accomplishing only 85 cents of planned work for every dollar scheduled
-
C
The project has overspent by 15%
-
D
The project will finish 15% early