Which scheduling technique uses three time estimates (optimistic, pessimistic, most likely) to calculate expected activity durations?
-
A
Critical Path Method (CPM)
-
B
Program Evaluation and Review Technique (PERT)
-
C
Monte Carlo simulation
-
D
Resource leveling