A PMO is asked to implement a 'toll gate' process. What does this governance mechanism do?
-
A
Charges projects for shared PMO services
-
B
Requires formal go/no-go approval at predefined decision points before proceeding
-
C
Limits the number of projects a manager can run simultaneously
-
D
Automates project status reporting to executives