A project manager discovers mid-project that a vendor is consistently delivering materials two weeks late. Which contract clause would BEST give the buyer leverage to remedy this situation?
-
A
Force majeure clause
-
B
Liquidated damages clause
-
C
Indemnification clause
-
D
Warranty clause