On a project, the cumulative CPI is 0.78 after consuming 60% of the schedule. Statistically, what is the most likely outcome?
-
A
The project will recover and finish within budget
-
B
The final CPI will likely remain near 0.78, resulting in a cost overrun
-
C
Management corrective actions will bring CPI above 1.0
-
D
The CPI is too early to be predictive