(CPP) Certified Project Professional Practice Test

CPP Earned Value Management 2

Free · Instant Results

A project has a Budget at Completion (BAC) of $200,000 and is 40% complete at the scheduled midpoint. The actual cost so far is $95,000. What is the Cost Performance Index (CPI)?
▶ Start Practice Test