A project manager discovers mid-project that actual costs are running 15% above the budget baseline. Which response is MOST appropriate under CPP standards?
-
A
Request additional funding immediately
-
B
Perform variance analysis and update the cost forecast
-
C
Reduce project scope to match the original budget
-
D
Pause all expenditures until the sponsor approves