What does a Schedule Performance Index (SPI) value of 0.85 indicate?
-
A
The project is 15% ahead of schedule
-
B
The project is only accomplishing 85 cents of scheduled work for every dollar of work planned
-
C
The project has a 15% cost overrun
-
D
The project team is 85% efficient