Which of the following is an example of a 'level production strategy' in aggregate planning?
-
A
Hiring and laying off workers to match demand fluctuations each month
-
B
Maintaining a constant workforce and production rate while using inventory to absorb demand variation
-
C
Outsourcing production during peak demand periods
-
D
Adjusting prices to shift demand away from peak periods