FREE Certified in Production and Inventory Management Sample Questions and Answers
What is a Hoshin planning objective?
Actual output divided by standard output is expressed as follows:
The ratio of actual output to standard output is defined as efficiency.
Which of the following factors may be predicted using the capability index?
Capability index is useful to predict process variability. It is a statistical measure of a process's ability to produce output within specification limits (Upper Specification Limit - USL and Lower Specification Limit - LSL) based on the process mean and standard deviation. It is commonly used to determine whether a process is capable of meeting customer requirements and is calculated as the ratio of the width of the specification limits to the spread of the process data.
In order to keep the time buffer queue full, the operation that manages the work feeding the bottleneck must run at a pace equal to the bottleneck's throughput.
The operation that controls the work feeding the bottleneck and must operate at a rate equal to the output of the bottleneck so the time buffer queue is maintained is known as a "drum" operation.
The following terms describe a facility, function, department, or resource whose capacity is equal to or lower than the demand placed upon it:
A facility, function, department, or resource whose capacity is equal to or less than the demand placed upon it is known as a bottleneck.
Which file includes a list of the single-level parts and quantities required to put a parent together?
The product structure file contains a list of the single-level components and quantities needed to assemble a parent.
Which file includes a list of the single-level parts and quantities required to put a parent together?
The file that contains a list of the single-level components and quantities needed to assemble a parent is called the "product structure file".