What are the three primary inputs to Material Requirements Planning (MRP)?
-
A
Purchase orders, work orders, and invoices
-
B
Master production schedule, bill of materials, and inventory records
-
C
Sales orders, capacity plan, and supplier contracts
-
D
Production plan, labor standards, and machine rates