What is the primary purpose of a 'Schedule Variance (SV)' in Earned Value Management?
-
A
To measure cost efficiency of work performed
-
B
To quantify the schedule deviation in monetary terms between earned and planned value
-
C
To forecast the final project completion date
-
D
To determine the remaining budget available for the project