CPE Cheat Sheet 2026

The 30 highest-yield CPE facts, distilled from real exam questions. Print it, save it as a PDF, or study it here — free, no sign-up.

180 questions
230 min time limit
70.00% to pass
  1. If a project's NPV is zero, the actual return on investment equals: The discount rate used
  2. What does a negative Cost Variance (CV) indicate? The project is over budget
  3. Which percent-complete measurement method is most objective for construction activities? Units completed method — units of work done divided by total units
  4. What is the purpose of a Hammock activity in project scheduling? To summarize a group of activities spanning between two points
  5. What distinguishes a Certified Planning Engineer certified professional from non-certified practitioners? Validated competency through standardized assessment
  6. Variance at Completion (VAC) is calculated as: BAC - EAC
  7. How should a CPE manager address underperformance? Provide timely feedback with support and a clear improvement plan
  8. On a CPE exam context, 'expected monetary value' (EMV) of a risk is calculated as: Probability × Impact
  9. In a Linear Scheduling Method (LSM) or Time-Chainage diagram, the slope of an activity line represents: The production rate or velocity of the activity
  10. In schedule performance reporting, a Milestone Trend Analysis (MTA) chart plots: The forecast finish date of key milestones over successive reporting periods
  11. In schedule network analysis, what is the significance of a 'Near-Critical Path'? It has small total float and could become critical if activities are delayed
  12. Estimate at Completion (EAC) using the formula EAC = BAC / CPI assumes: Future cost performance will match current CPI
  13. The 'Cost of Quality' concept includes which two main categories of costs? Conformance costs and non-conformance costs
  14. When applying the three-point estimating (PERT) formula for cost, what weights are applied to optimistic (O), most likely (M), and pessimistic (P)? O×1, M×4, P×1 divided by 6
  15. When performing 'What-If Scenario Analysis' in scheduling, the planner typically: Models alternative scenarios to evaluate the impact of risks or changes
  16. How does the CPE body of knowledge relate to daily practice? Provides the framework guiding decisions and standard practices
  17. What is the difference between quality assurance and quality control? Processes vs product inspection
  18. When conducting a risk assessment for CPE operations, which factor gets HIGHEST priority? Probability and severity of potential harm
  19. A contractor submits a claim for 'constructive acceleration.' This means: The owner directed faster work without a formal order
  20. Which communication artifact is most critical for keeping project stakeholders aligned on schedule status in a CPE-managed project? Progress S-curve with earned value overlay
  21. A project has a Benefit-Cost Ratio (BCR) of 0.85. What does this indicate? The project returns $0.85 for every $1 invested
  22. Which Work Breakdown Structure (WBS) level directly feeds into the project schedule as schedulable activities? Work Packages
  23. A Schedule Performance Index (SPI) of 0.85 indicates that the project is: Behind schedule — only 85 cents of scheduled work completed per dollar planned
  24. The Estimate at Completion (EAC) formula EAC = BAC / CPI is used when: Current cost performance is expected to continue for the remainder of the project
  25. What is the goal of risk management in projects? Identify and mitigate risks
  26. A parametric cost model for construction estimates $250 per square foot. If the building is 10,000 sq ft, what is the estimated cost? $2,500,000
  27. A Fishbone (Ishikawa) diagram is primarily used in quality management to: Identify root causes of quality problems
  28. A project's Baseline Execution Index (BEI) is used to measure: The ratio of activities completed on time vs. those that were planned to be complete
  29. Under the American Institute of Architects (AIA) A201 General Conditions, a 'Change Order' requires agreement from: Owner, contractor, and architect
  30. A stakeholder matrix in project planning is used primarily to: Identify stakeholder influence and interest to tailor communication strategies
Turn these facts into recall:
Was this helpful?