On a large EPC project, the owner directs the contractor to accelerate the completion date by three months. What is the FIRST step the contractor's planning engineer should take?
-
A
Immediately update the project schedule to reflect the new completion date
-
B
Evaluate the cost and resource impact of acceleration and submit a change request
-
C
Advise the owner that acceleration is not possible
-
D
Reduce float on all activities and update the baseline