Which of the following changes would typically require a formal baseline change rather than being absorbed within existing management reserve?
-
A
A minor rework due to a quality inspection failure
-
B
A customer-directed addition of a significant new deliverable
-
C
A small cost overrun on a single work package
-
D
A one-week weather delay on a non-critical path activity