A project's EAC is calculated as AC + (BAC - EV). This formula assumes:
-
A
Future work will continue at the current CPI
-
B
The remaining work will be completed at the originally planned rate
-
C
The project will experience the same variance as to date
-
D
Future performance will be worse than current CPI