Which communication artifact is most critical for keeping project stakeholders aligned on schedule status in a CPE-managed project?
-
A
Weekly email blast
-
B
Baseline schedule narrative report
-
C
Progress S-curve with earned value overlay
-
D
Meeting minutes only