A Planning Engineer receives conflicting schedule inputs from two subcontractors. The BEST resolution approach is to:
-
A
Use the more optimistic schedule without discussion
-
B
Facilitate an interface meeting to resolve logic conflicts before updating the master schedule
-
C
Submit both schedules to the owner and let them decide
-
D
Ignore one input entirely