A client's executive sponsor becomes unresponsive during a critical phase of the implementation. What is the BEST first step?
-
A
Escalate immediately to the client's board of directors
-
B
Engage the sponsor's direct reports to proceed without approval
-
C
Send a formal communication documenting the impact of the delay and request a meeting
-
D
Pause all implementation activities until the sponsor responds