CHST Emergency and Fire Preparedness 5 — Questions and Answers
Question 1: A construction worker notices smoke coming from electrical conduit inside a wall cavity. Which type of fire extinguisher is appropriate?
- Class A water extinguisher
- Class B CO2 extinguisher
- Class C-rated extinguisher (Correct answer)
- Class D dry powder extinguisher
Correct answer: Class C-rated extinguisher
Electrical fires require a Class C-rated extinguisher because water-based agents conduct electricity and could endanger the user.
Question 2: What is the minimum frequency required for inspecting portable fire extinguishers on a construction site under OSHA standards?
- Daily
- Weekly
- Monthly (Correct answer)
- Annually
Correct answer: Monthly
OSHA requires monthly visual inspections of portable fire extinguishers to ensure they are in place, fully charged, and operational.
Question 3: During a hazardous materials spill emergency on a construction site, which document should first-responders reference to identify safe handling procedures?
- The site's project schedule
- The Safety Data Sheet (SDS) for the material (Correct answer)
- The general contractor's insurance policy
- OSHA Form 300 injury log
Correct answer: The Safety Data Sheet (SDS) for the material
The Safety Data Sheet (SDS) provides critical information on hazards, PPE requirements, and emergency response procedures for a specific chemical.
Question 4: Which scenario requires a site to implement an Incident Command System (ICS) structure during an emergency?
- A single worker receives a minor laceration
- A multi-agency response to a structural collapse with multiple victims (Correct answer)
- A brief power outage lasting less than 15 minutes
- A subcontractor replaces a damaged tool
Correct answer: A multi-agency response to a structural collapse with multiple victims
ICS is designed for complex, multi-agency emergencies such as structural collapses where coordinated command and communication are critical.
Question 5: What is the correct sequence for using a portable fire extinguisher, remembered by the acronym PASS?
- Pull, Aim, Sweep, Squeeze
- Pull, Aim, Squeeze, Sweep (Correct answer)
- Press, Aim, Squeeze, Spray
- Prepare, Activate, Spray, Secure
Correct answer: Pull, Aim, Squeeze, Sweep
PASS stands for Pull the pin, Aim at the base of the fire, Squeeze the handle, and Sweep side to side across the base of the flames.
Question 6: On a multi-employer construction site, who bears primary responsibility for ensuring emergency telephone numbers are posted?
- Each individual subcontractor independently
- The controlling employer or general contractor (Correct answer)
- The local municipality
- OSHA's area office
Correct answer: The controlling employer or general contractor
The general contractor (controlling employer) is responsible for overall site safety coordination, including posting emergency contact numbers prominently.
Question 7: A propane-fueled salamander heater ignites nearby lumber during winter concrete curing work. What should the site superintendent do FIRST?
- Attempt to move the burning lumber
- Activate the site alarm and initiate evacuation (Correct answer)
- Call the site owner for permission to respond
- Wait to assess how large the fire becomes
Correct answer: Activate the site alarm and initiate evacuation
Activating the alarm and initiating evacuation is the immediate priority to protect worker lives before attempting any fire control measures.
A construction worker notices smoke coming from electrical conduit inside a wall cavity.
Which type of fire extinguisher is appropriate?