A CHST is pressured by a project manager to sign off on a scaffold inspection knowing the scaffold does not meet OSHA standards. According to BCSP's Code of Ethics, the CHST should:
-
A
Sign off to maintain the professional relationship, then document concerns privately
-
B
Refuse to certify the scaffold and report the deficiency through appropriate channels
-
C
Request that another safety professional inspect and potentially certify it
-
D
Advise workers verbally of the hazard but sign the form to avoid conflict