CHST - Construction Health and Safety Technician Electrical Safety and LOTO Questions and Answers 1

Free ยท Instant Results

An electrician is preparing to work on a 480-volt motor control center. After shutting off the main breaker that supplies the MCC, what is the most critical next step they must perform before beginning work?