Stormwater Management Practices Flashcards

21 cards from real CESSWI practice questions. Tap to flip, then mark Knew It or Still Learning — missed cards come back until you master them.

Read the first 20 Stormwater Management Practices flashcards as text
  1. Which type of detention basin is designed to drain completely between storm events, providing no permanent pool of water?

    Answer: Dry detention basin

    Dry detention basins (also called dry ponds) temporarily store runoff and drain completely between storms, providing only flood control without water quality benefits from a permanent pool.

  2. What is the primary purpose of an extended detention basin compared to a standard dry detention basin?

    Answer: Provide longer residence time to settle fine sediments

    Extended detention basins hold runoff for 24–40 hours, allowing finer sediment particles that would not settle in a standard detention period to be removed before release.

  3. A bioretention cell (rain garden) treats stormwater primarily through which combination of processes?

    Answer: Filtration, infiltration, and biological uptake

    Bioretention cells use engineered soil media for filtration, underlying native soil for infiltration, and plants for biological nutrient uptake to achieve pollutant removal.

  4. Under the NPDES Construction General Permit, what minimum rainfall threshold typically triggers the requirement to inspect a construction site for BMPs?

    Answer: 0.25 inch

    Most NPDES Construction General Permits require post-storm inspections following rainfall events of 0.25 inch or greater within a 24-hour period.

  5. Which outlet structure configuration is best suited to control two separate design storms (e.g., 2-year and 100-year) from a single detention basin?

    Answer: Riser with multiple orifices at different elevations

    A multi-stage riser with orifices at different elevations independently controls smaller, more frequent storms at lower stages and larger storms at higher stages.

  6. What term describes the volume of runoff that must be captured and treated to meet water quality objectives under many state stormwater programs?

    Answer: Water quality volume (WQv)

    The Water Quality Volume (WQv) is the runoff volume associated with a small, frequent storm (often the 90th percentile event) that must be captured and treated to achieve pollutant load reductions.

  7. Permeable pavement systems reduce stormwater runoff volume primarily by:

    Answer: Allowing water to infiltrate through voids into underlying storage layers

    Permeable pavement contains open-graded voids that allow rainfall to pass through the surface and into a stone reservoir base, where it infiltrates into the subgrade or is slowly released.

  8. In a constructed stormwater wetland, the shallow marsh zone typically operates at what average water depth to support emergent vegetation?

    Answer: 6–18 inches

    The shallow marsh zone of a constructed wetland is typically maintained at 6–18 inches depth, which supports emergent plants like cattails and bulrushes that provide biological treatment.

  9. Which BMP design parameter ensures that sediment trapped in a basin will not be resuspended and discharged during large storm events?

    Answer: Length-to-width ratio

    A length-to-width ratio of 3:1 or greater promotes plug flow, reducing turbulence and short-circuiting that could resuspend settled sediment during high-flow events.

  10. A stormwater harvesting system (cistern or rain barrel) primarily reduces which component of the urban water cycle?

    Answer: Runoff volume by capturing and reusing rainfall

    Stormwater harvesting captures rooftop runoff for non-potable reuse (irrigation, toilet flushing), directly reducing the volume of stormwater discharged to drainage systems.

  11. When inspecting a grassed swale, which condition indicates that the swale is NOT functioning properly?

    Answer: Rill erosion channels and bare soil visible along the flow path

    Rill erosion and bare soil in a grassed swale indicate that flow velocities are exceeding permissible limits or vegetation is inadequate, causing erosion rather than filtration.

  12. The rational method equation Q = CiA calculates peak runoff rate. What does the coefficient 'C' represent?

    Answer: Runoff coefficient reflecting land cover and soil type

    The runoff coefficient C (dimensionless, 0–1.0) accounts for the fraction of rainfall that becomes surface runoff based on land use, soil type, and slope.

  13. What is the purpose of a forebay in a stormwater pond or wetland design?

    Answer: Pre-settle coarse sediment near the inlet to protect the main pool

    A forebay is a smaller, deeper cell at the inlet that traps coarse sediment and debris before flow enters the main treatment area, making sediment removal easier and protecting the main pool.

  14. Under Low Impact Development (LID) principles, what is the primary goal when managing stormwater from a new development?

    Answer: Mimic pre-development hydrology by managing runoff at the source

    LID aims to replicate pre-development hydrology through distributed, small-scale practices that promote infiltration, evapotranspiration, and retention close to where rain falls.

  15. Which soil hydrologic group has the highest infiltration rates and is best suited for infiltration-based stormwater BMPs?

    Answer: Group A

    HSG A soils (deep sands, well-drained gravels) have the lowest runoff potential and highest infiltration rates, making them ideal for infiltration trenches, basins, and permeable pavement.

  16. A stormwater inspector finds that the emergency spillway of a detention pond has been blocked by debris. What is the primary risk this creates?

    Answer: Potential for dam overtopping and embankment failure during extreme storms

    The emergency spillway protects the embankment from overtopping; if blocked, flows exceeding the principal outlet capacity could overtop and rapidly erode the embankment, leading to failure.

  17. Green roofs reduce stormwater runoff volume primarily by:

    Answer: Retaining rainfall in growing media and releasing it through evapotranspiration

    Green roof growing media absorb rainfall and plants release stored water through evapotranspiration, significantly reducing the volume and peak rate of runoff from rooftops.

  18. What design feature of a wet detention pond prevents short-circuiting of flow from inlet to outlet?

    Answer: Placement of inlet and outlet at opposite ends with a minimum 3:1 length-to-width ratio

    Separating the inlet and outlet at opposite ends and maintaining a 3:1 or greater length-to-width ratio maximizes flow path length, promoting settling and reducing short-circuit pathways.

  19. When performing a post-construction stormwater inspection, which document should the inspector reference to verify that BMPs were installed as approved?

    Answer: The approved stormwater management plan and construction drawings

    The approved stormwater management plan and associated construction drawings define the required BMP types, sizes, locations, and specifications that the inspector verifies against field conditions.

  20. Which pollutant is most effectively removed from stormwater by a vegetated filter strip?

    Answer: Coarse sediment and associated particulate pollutants

    Vegetated filter strips excel at removing coarse sediment through deposition and filtration as sheet flow passes through dense vegetation, along with particulate-bound pollutants.

Written and edited by , founder of Practice Test Geeks, with AI assistance. Exam facts are checked against the official sources linked below. Editorial policy

Sources & references

Exam facts on this page (fees, format, dates, passing scores) are checked against these official sources; the date is our last check. Editorial policy

  1. envirocert.org — Eligibility, fees, renewal, score validity, test delivery, score release, retake fee · verified Nov 2026