Question 1: Under the Clean Water Act Section 402, which program specifically governs stormwater discharges from construction sites?
- Section 404 Dredge and Fill Program
- National Pollutant Discharge Elimination System (NPDES) (Correct answer)
- Total Maximum Daily Load (TMDL) Program
- Section 319 Nonpoint Source Program
Correct answer: National Pollutant Discharge Elimination System (NPDES)
The NPDES program under CWA Section 402 regulates point source discharges including stormwater from construction activities.
Question 2: A construction site disturbing 0.8 acres is located in a state that has been authorized by EPA to administer its own NPDES program. Which permit authority applies?
- The site is exempt because it is under 1 acre
- EPA issues the federal NPDES permit directly
- The state issues its own equivalent permit under state authority (Correct answer)
- No permit is required until the site exceeds 5 acres
Correct answer: The state issues its own equivalent permit under state authority
In states with EPA-authorized NPDES programs, the state administers its own stormwater permits and the state permit applies.
Question 3: Which EPA Phase II rule expanded NPDES stormwater permit requirements to include construction sites of what minimum acreage?
- 5 acres or more
- 2 acres or more
- 1 acre or more (Correct answer)
- 0.5 acres or more
Correct answer: 1 acre or more
The EPA Phase II stormwater rule (effective 2003) extended permit requirements to construction sites disturbing 1 acre or more.
Question 4: What is the primary purpose of a Stormwater Pollution Prevention Plan (SWPPP) under the Construction General Permit?
- To estimate project costs for erosion control materials
- To document BMPs and site conditions to prevent pollutant discharge (Correct answer)
- To satisfy local zoning and land-use approval requirements
- To calculate the peak discharge rate for drainage design
Correct answer: To document BMPs and site conditions to prevent pollutant discharge
A SWPPP identifies BMPs and site-specific measures to prevent stormwater pollution from reaching waters of the United States.
Question 5: Under the EPA Construction General Permit, operators must conduct routine inspections of BMPs at least how frequently during active construction?
- Once per month
- Every 14 calendar days and within 24 hours of a 0.25-inch rain event (Correct answer)
- Weekly regardless of weather conditions
- Daily during all grading operations
Correct answer: Every 14 calendar days and within 24 hours of a 0.25-inch rain event
The EPA CGP requires inspections every 14 days and within 24 hours of a qualifying storm event to verify BMP effectiveness.
Question 6: Which of the following is NOT typically required to be included in a SWPPP?
- Site map showing drainage patterns and BMP locations
- Description of potential pollutant sources
- Contractor's liability insurance certificate (Correct answer)
- Inspection and maintenance procedures for BMPs
Correct answer: Contractor's liability insurance certificate
Insurance certificates are not a SWPPP regulatory requirement; the plan must address pollution prevention, not contractor finances.
Question 7: When a construction project is complete and all areas are stabilized, what must the permit holder file to terminate NPDES permit coverage?
- A Notice of Termination (NOT) (Correct answer)
- A Certificate of Occupancy
- A Final Inspection Report
- A Notice of Intent (NOI) amendment
Correct answer: A Notice of Termination (NOT)
A Notice of Termination (NOT) is submitted to the permitting authority once the site is stabilized and permit coverage is no longer needed.
Under the Clean Water Act Section 402, which program specifically governs stormwater discharges from construction sites?