Question 1: Under the Clean Water Act Section 402, which program specifically governs stormwater discharges from construction sites?
- Section 404 Dredge and Fill Program
- National Pollutant Discharge Elimination System (NPDES) (Correct answer)
- Total Maximum Daily Load (TMDL) Program
- Section 319 Nonpoint Source Program
Correct answer: National Pollutant Discharge Elimination System (NPDES)
The NPDES program under CWA Section 402 regulates point source discharges including stormwater from construction activities.
Question 2: A construction site disturbing 0.8 acres is located in a state that has been authorized by EPA to administer its own NPDES program. Which permit authority applies?
- The site is exempt because it is under 1 acre
- EPA issues the federal NPDES permit directly
- The state issues its own equivalent permit under state authority (Correct answer)
- No permit is required until the site exceeds 5 acres
Correct answer: The state issues its own equivalent permit under state authority
In states with EPA-authorized NPDES programs, the state administers its own stormwater permits and the state permit applies.
Question 3: Which EPA Phase II rule expanded NPDES stormwater permit requirements to include construction sites of what minimum acreage?
- 5 acres or more
- 2 acres or more
- 1 acre or more (Correct answer)
- 0.5 acres or more
Correct answer: 1 acre or more
The EPA Phase II stormwater rule (effective 2003) extended permit requirements to construction sites disturbing 1 acre or more.
Question 4: What is the primary purpose of a Stormwater Pollution Prevention Plan (SWPPP) under the Construction General Permit?
- To estimate project costs for erosion control materials
- To document BMPs and site conditions to prevent pollutant discharge (Correct answer)
- To satisfy local zoning and land-use approval requirements
- To calculate the peak discharge rate for drainage design
Correct answer: To document BMPs and site conditions to prevent pollutant discharge
A SWPPP identifies BMPs and site-specific measures to prevent stormwater pollution from reaching waters of the United States.
Question 5: Under the EPA Construction General Permit, operators must conduct routine inspections of BMPs at least how frequently during active construction?
- Once per month
- Every 14 calendar days and within 24 hours of a 0.25-inch rain event (Correct answer)
- Weekly regardless of weather conditions
- Daily during all grading operations
Correct answer: Every 14 calendar days and within 24 hours of a 0.25-inch rain event
The EPA CGP requires inspections every 14 days and within 24 hours of a qualifying storm event to verify BMP effectiveness.
Question 6: Which of the following is NOT typically required to be included in a SWPPP?
- Site map showing drainage patterns and BMP locations
- Description of potential pollutant sources
- Contractor's liability insurance certificate (Correct answer)
- Inspection and maintenance procedures for BMPs
Correct answer: Contractor's liability insurance certificate
Insurance certificates are not a SWPPP regulatory requirement; the plan must address pollution prevention, not contractor finances.
Question 7: When a construction project is complete and all areas are stabilized, what must the permit holder file to terminate NPDES permit coverage?
- A Notice of Termination (NOT) (Correct answer)
- A Certificate of Occupancy
- A Final Inspection Report
- A Notice of Intent (NOI) amendment
Correct answer: A Notice of Termination (NOT)
A Notice of Termination (NOT) is submitted to the permitting authority once the site is stabilized and permit coverage is no longer needed.
Question 8: Under the CWA, 'waters of the United States' (WOTUS) is important because it defines the geographic scope of which regulatory program?
- Federal floodplain management under NFIP
- NPDES permit jurisdiction and Section 404 wetland permits (Correct answer)
- State drinking water source protection programs
- OSHA construction site safety regulations
Correct answer: NPDES permit jurisdiction and Section 404 wetland permits
WOTUS defines which water bodies fall under federal CWA jurisdiction, triggering NPDES and Section 404 permit requirements.
Question 9: A contractor installs a concrete washout area on-site without any liner. Which regulatory concern does this most directly trigger?
- Violation of OSHA hazard communication standards
- Potential unpermitted discharge of pH-elevated wastewater to stormwater (Correct answer)
- Violation of local solid waste disposal ordinances only
- Noncompliance with FEMA floodplain development regulations
Correct answer: Potential unpermitted discharge of pH-elevated wastewater to stormwater
Unlined concrete washouts can leach alkaline wastewater into stormwater, constituting an unpermitted pollutant discharge under NPDES.
Question 10: Section 404 of the Clean Water Act requires a permit from the U.S. Army Corps of Engineers (USACE) for which activity?
- Stormwater discharges from construction sites exceeding 1 acre
- Discharge of dredged or fill material into waters of the United States (Correct answer)
- Installation of sediment basins on upland areas
- Grading and grubbing activities more than 50 feet from a waterway
Correct answer: Discharge of dredged or fill material into waters of the United States
Section 404 permits issued by USACE are required for discharging dredged or fill material into jurisdictional waters and wetlands.
Question 11: What does a Total Maximum Daily Load (TMDL) establish for an impaired water body?
- The maximum volume of stormwater that can be discharged daily
- The maximum amount of a pollutant a water body can receive and still meet water quality standards (Correct answer)
- The required frequency of stormwater monitoring at construction sites
- The minimum buffer distance required between construction and waterways
Correct answer: The maximum amount of a pollutant a water body can receive and still meet water quality standards
A TMDL sets the maximum pollutant load a water body can assimilate while still meeting applicable water quality standards.
Question 12: A CESSWI inspector discovers that a permitted construction site is discharging turbid stormwater directly to a stream without functional BMPs. What is the most appropriate immediate action?
- Issue an immediate stop-work order under federal authority
- Document the violation, notify the site operator, and report to the permitting authority (Correct answer)
- Contact FEMA to activate the National Flood Insurance Program
- Require the contractor to halt all work until EPA provides written guidance
Correct answer: Document the violation, notify the site operator, and report to the permitting authority
Inspectors document noncompliance and notify operators and the regulatory authority; federal enforcement authority rests with the permitting agency, not the inspector.
Question 13: Which federal agency has primary enforcement authority for NPDES violations at construction sites in states without authorized NPDES programs?
- U.S. Army Corps of Engineers
- Federal Emergency Management Agency (FEMA)
- U.S. Environmental Protection Agency (EPA) (Correct answer)
- U.S. Department of Agriculture Natural Resources Conservation Service
Correct answer: U.S. Environmental Protection Agency (EPA)
EPA retains direct NPDES enforcement authority in states that have not received EPA authorization to administer their own permit programs.
Question 14: Under the EPA Construction General Permit, which of the following pollutants from construction sites requires specific BMP controls beyond sediment?
- Carbon dioxide from equipment exhaust
- Concrete washout, paint, and fuel stored on site (Correct answer)
- Noise from grading equipment
- Dust from unpaved access roads in arid regions
Correct answer: Concrete washout, paint, and fuel stored on site
The CGP requires BMPs to address non-sediment pollutants including concrete washout, fuels, oils, paints, and other chemicals stored or used on site.
Question 15: A state requires that construction sites implement post-construction stormwater controls as a condition of local land development approval. This requirement is most directly associated with which federal mandate?
- NPDES Phase II stormwater rules requiring local MS4 programs to include post-construction standards (Correct answer)
- Section 404 wetland mitigation banking regulations
- The National Environmental Policy Act (NEPA) environmental review process
- The Endangered Species Act Section 7 consultation requirements
Correct answer: NPDES Phase II stormwater rules requiring local MS4 programs to include post-construction standards
Phase II NPDES rules require Municipal Separate Storm Sewer System (MS4) programs to establish post-construction stormwater management standards for new development.
Question 16: Which document must a construction operator file BEFORE earth disturbance begins at a site requiring NPDES permit coverage?
- Notice of Termination (NOT)
- Notice of Intent (NOI) (Correct answer)
- Discharge Monitoring Report (DMR)
- Environmental Impact Statement (EIS)
Correct answer: Notice of Intent (NOI)
Operators must file a Notice of Intent (NOI) to be covered under the Construction General Permit before disturbing any earth.
Question 17: Under most state construction general permits, what is the maximum allowable turbidity or visual benchmark that inspectors use to evaluate whether a BMP is functioning effectively?
- Discharge must be completely clear with zero suspended solids
- Discharge must not cause a visible sheen, foam, or floating solids in receiving waters
- Discharge must not cause a discernible change in the color or clarity of the receiving water (Correct answer)
- Discharge turbidity must not exceed 5 NTU above background levels
Correct answer: Discharge must not cause a discernible change in the color or clarity of the receiving water
Many permits use narrative standards prohibiting discharges that cause a discernible change in color or clarity of receiving waters as the visual benchmark.
Question 18: When multiple operators share responsibility on a single construction site under a Construction General Permit, how is permit responsibility typically allocated?
- Only the general contractor holds permit responsibility; subcontractors are exempt
- Each operator with operational control over a portion of the site may need separate or co-permittee coverage (Correct answer)
- The landowner always holds sole permit responsibility regardless of who performs work
- Permit responsibility automatically transfers to whoever installs the sediment controls
Correct answer: Each operator with operational control over a portion of the site may need separate or co-permittee coverage
Operators with day-to-day operational control over site activities may each require permit coverage or be named as co-permittees.
Question 19: A construction site inspector finds that rain gauge records show a 0.3-inch storm occurred 20 hours ago, but no post-storm BMP inspection was conducted. Under the EPA CGP, this is a violation because:
- Inspections are required within 24 hours of any rain event regardless of amount
- Inspections are required within 24 hours of a storm producing 0.25 inches or more of rainfall (Correct answer)
- All inspections must be completed before any storm event is forecast
- Post-storm inspections are only required after storms exceeding 1 inch
Correct answer: Inspections are required within 24 hours of a storm producing 0.25 inches or more of rainfall
The EPA CGP requires inspections within 24 hours of a storm event that produces 0.25 inches or more of rainfall.
Question 20: Which of the following best describes an 'operator' as defined under NPDES construction stormwater regulations?
- Any subcontractor performing earthwork activities on the project
- Any entity with operational control over daily activities or the ability to modify plans/specifications (Correct answer)
- The licensed engineer who stamps the SWPPP drawings
- The municipality issuing the grading permit for the project
Correct answer: Any entity with operational control over daily activities or the ability to modify plans/specifications
An 'operator' is any entity that has operational control over construction activities or control over the project's plans and specifications.
Question 21: A linear construction project (pipeline) crosses through three states. Which NPDES permits are required?
- A single federal NPDES permit from EPA covers the entire linear project
- Separate NPDES permit coverage is required in each state where earth disturbance occurs (Correct answer)
- Only one permit from the state where the project originates is needed
- Linear projects are exempt from NPDES requirements regardless of disturbed acreage
Correct answer: Separate NPDES permit coverage is required in each state where earth disturbance occurs
NPDES permit coverage must be obtained in each state where land disturbance occurs, as each state (or EPA for unauthorized states) has its own jurisdiction.
Under the Clean Water Act Section 402, which program specifically governs stormwater discharges from construction sites?
What Practice Test Geeks adds beyond an AI chat for CESSWI
An AI chatbot can quiz you, but it can't reproduce the exam conditions or keep your record. Here you get:
- A timed, full-length CESSWI mock exam — 100 questions in 120 minutes with a 75% pass mark, modeled on the official exam's question count and time limit, followed by a score report broken down by exam domain.
- A fixed CESSWI question bank: the same test every attempt, so your score is comparable from one try to the next instead of changing with every regenerated quiz.
- Progress saved on your device: completed tests, scores and missed questions stay in My Progress, so you can retake only what you got wrong.
- A printable CESSWI cheat sheet you can print or save as a PDF.
- CESSWI flashcards built from the same question bank.
Practice questions written with AI assistance and published by Nathan Beja, founder of Practice Test Geeks. They are not real exam questions. Exam facts are checked against the official sources linked below. Editorial policy
Sources & references
Exam facts on this page (fees, format, dates, passing scores) are checked against these official sources; the date is our last check. Editorial policy
- envirocert.org — Eligibility, fees, renewal, score validity, test delivery, score release, retake fee · verified Nov 2026