What is the primary purpose of a supply chain risk register?
Answer: To document identified risks with their likelihood, impact, owner, and planned response
A risk register is the central record of identified risks, their assessment, ownership, and response plans.
A company identifies a minor risk whose mitigation would cost more than the expected loss. Which response strategy is most appropriate?
Answer: Risk acceptance
When mitigation costs exceed the expected loss, accepting the risk (with monitoring) is usually the most economical choice.
A port strike has a 10% probability of occurring and would cause a $500,000 loss. What is its expected monetary value (EMV)?
Answer: $50,000
EMV equals probability multiplied by impact: 0.10 x $500,000 = $50,000.
How does a business continuity plan (BCP) differ from a disaster recovery (DR) plan?
Answer: A BCP keeps critical business functions operating overall, while DR focuses mainly on restoring IT systems and data
Business continuity addresses sustaining critical operations broadly, whereas disaster recovery is typically the IT-focused subset.
What is the main supply risk associated with single sourcing a critical component?
Answer: No alternate source is available if that supplier is disrupted
Single sourcing concentrates dependency, so any disruption at that supplier can halt supply entirely.
Which action is an example of risk transfer?
Answer: Purchasing cargo insurance for international shipments
Insurance shifts the financial consequence of a risk to a third party, which defines risk transfer.
In continuity planning, what does the recovery time objective (RTO) define?
Answer: The maximum acceptable time to restore a process after a disruption
RTO sets the target maximum duration a process can be down before unacceptable consequences occur.
How this page was made: written with AI tools and published by Nathan Beja, founder of Practice Test Geeks, who is responsible for its content. Exam facts are checked against the official sources listed below. Not reviewed by a subject-matter expert. Editorial policy
Sources & references
Exam facts on this page (fees, format, dates, passing scores) are checked against these official sources; the date is our last check. Editorial policy
- ascm.org — Renewal, score validity, retake policy, score release, test delivery, exam format, passing score, retake fee, test dates, eligibility · verified Nov 2026