1. What is the most common mistake professionals make when implementing project management strategies?
Developing contingency plans for high-probability risk scenarios is the correct approach because effective project management in the associate constructor field requires adherence to professional standards, evidence-based practices, and systematic methodology. This approach ensures consistent, high-quality outcomes while maintaining professional accountability.
2. Which AIA contract document is most commonly used for a stipulated sum agreement between owner and contractor?
AIA A101 is the standard form of agreement between owner and contractor for a stipulated (fixed) sum.
3. PERT (Program Evaluation and Review Technique) uses three time estimates for each activity. What are they?
PERT uses optimistic (O), most likely (M), and pessimistic (P) durations to calculate a weighted average expected time for each activity.
4. A schedule that has been loaded with cost information for each activity is called a:
A cost-loaded schedule assigns dollar values to each activity, enabling the generation of S-curves and progress payment applications tied to schedule performance.
5. What is 'fast-tracking' in construction project scheduling?
Fast-tracking compresses the schedule by performing phases in parallel rather than sequentially, though it often increases risk and coordination demands.
6. What does the term 'differing site conditions' (DSC) mean in US construction contracts?
A Differing Site Condition clause allows contractors to claim equitable adjustment when actual subsurface conditions differ materially from what the contract documents indicated.