The Agile principle of 'responding to change over following a plan' most directly impacts process design by:
-
A
Eliminating all planning activities from process workflows
-
B
Building processes that can be adapted quickly as requirements evolve
-
C
Requiring plans to be rewritten whenever a change is requested
-
D
Limiting change requests to once per quarter