What is relative estimation in Agile?
-
A
Estimating tasks in actual clock hours compared to a baseline activity
-
B
Sizing work items by comparing their complexity to one another rather than assigning absolute values
-
C
Using past sprint data to predict exact completion dates
-
D
Estimating cost relative to the project budget