Under OSHA 29 CFR 1926.850, what must be done before demolition work begins on any structure?
-
A
Conduct an engineering survey to assess structure condition
-
B
Remove all windows and doors first
-
C
Install temporary lighting throughout the structure
-
D
Obtain a surety bond from the demolition contractor