CDS CDS Contract Administration & Documentation 1 — Questions and Answers
Question 1: What document formally defines the scope of work, terms, and obligations between a demolition contractor and the owner?
- Work Order
- Contract Agreement (Correct answer)
- Bid Bond
- Change Order
Correct answer: Contract Agreement
A contract agreement formally defines the scope, terms, and obligations between the demolition contractor and the project owner.
Question 2: What is the purpose of a bid bond in demolition contracting?
- Pay subcontractors upon award
- Guarantee the contractor will enter the contract if awarded (Correct answer)
- Cover project insurance costs
- Fund material purchases during mobilization
Correct answer: Guarantee the contractor will enter the contract if awarded
A bid bond guarantees that the bidder will enter into the contract and provide required performance bonds if awarded the project.
Question 3: Which document records all approved changes to the original contract scope, schedule, or price?
- Request for Information (RFI)
- Submittal Log
- Change Order (Correct answer)
- Daily Field Report
Correct answer: Change Order
A change order documents approved modifications to the contract's original scope, schedule, or cost.
Question 4: What does RFI stand for in demolition project documentation?
- Request for Inspection
- Request for Information (Correct answer)
- Report of Incident
- Record of Installation
Correct answer: Request for Information
RFI stands for Request for Information, used by contractors to clarify ambiguities or conflicts in project documents.
Question 5: A subcontract agreement primarily serves to:
- Replace the prime contract with the owner
- Document scope and payment terms between the GC and subcontractor (Correct answer)
- Satisfy OSHA recordkeeping requirements
- Obtain building and demolition permits
Correct answer: Document scope and payment terms between the GC and subcontractor
A subcontract agreement establishes the scope, schedule, and payment obligations between the general contractor and each subcontractor.
Question 6: Which tracking tool is used to monitor submittals, RFIs, and change orders throughout a demolition project?
- Project Schedule (Gantt Chart)
- Project Log or Submittal Log (Correct answer)
- Lien Waiver Register
- Notice to Proceed
Correct answer: Project Log or Submittal Log
A project log or submittal log tracks all submittals, RFIs, and change orders to ensure timely processing and project control.
What document formally defines the scope of work, terms, and obligations between a demolition contractor and the owner?