Under OSHA 29 CFR 1926.850, what must be done before demolition work begins?
-
A
Begin demolition immediately to reduce project costs
-
B
Conduct an engineering survey of the structure
-
C
Remove all workers from the site perimeter
-
D
Install permanent barricades around the building