During selective demolition, a QC inspector identifies unexpected asbestos-containing material (ACM) behind a wall. Under NESHAP regulations, what is the first required action?
-
A
Remove the material immediately using standard PPE
-
B
Stop work in the affected area and notify the project owner and regulatory agency
-
C
Cover the material and continue work in adjacent areas
-
D
Test additional samples before making any notifications