A demolition project is located adjacent to an active railroad. Which plan element is MOST critical to add to the project management documentation?
-
A
A railroad equipment rental budget
-
B
A third-party coordination and protection plan with railroad authority approval
-
C
Additional crew overtime schedule
-
D
A soil compaction testing plan