When a WCF business area's actual costs exceed its budgeted costs mid-year, the preferred course of action is to:
-
A
Immediately increase rates charged to customers during the current fiscal year
-
B
Absorb the variance and adjust rates in the next budget cycle
-
C
Request a direct supplemental appropriation from Congress
-
D
Transfer costs to a Military Department's O&M appropriation