Under DoD 5000.04-M, the primary purpose of an Independent Cost Estimate (ICE) is to:
-
A
Replace the contractor's proposal before negotiations
-
B
Provide an unbiased cost assessment separate from the program office estimate
-
C
Set the definitized contract price
-
D
Validate the contractor's earned value management system