← All CCBA Flashcard Decks

Requirements Elicitation & Documentation Flashcards

7 cards from real CCBA practice questions. Tap to flip, then mark Knew It or Still Learning — missed cards come back until you master them.

Read the first 7 Requirements Elicitation & Documentation flashcards as text
  1. A project team is experiencing frequent requirement changes after baseline approval. What is the MOST likely root cause?

    Answer: Requirements were not sufficiently validated with stakeholders before baselining

    High post-baseline volatility usually indicates that requirements were not adequately validated with the right stakeholders before sign-off, leaving gaps that surface later.

  2. What is 'gold plating' in the context of requirements, and why is it a problem?

    Answer: Implementing features beyond what stakeholders requested, consuming resources without authorized business value

    Gold plating occurs when the team adds unauthorized features, which wastes resources, may introduce defects, and was never validated as delivering business value.

  3. Which of the following is an example of a NON-FUNCTIONAL requirement?

    Answer: The system shall process 10,000 transactions per second with 99.9% uptime

    Non-functional requirements define system quality attributes such as performance, reliability, and availability, rather than specific behaviors or features.

  4. A BA documents an assumption that a third-party API will remain available throughout the project. Later, the API vendor discontinues it. What risk management action should the BA have taken?

    Answer: Logged the assumption as a risk and developed a contingency plan

    Every documented assumption should be assessed as a risk, since if the assumption proves false, it can impact requirements, scope, or delivery.

  5. What is the difference between a constraint and a requirement?

    Answer: A constraint is a restriction imposed on the solution; a requirement is a condition the solution must satisfy

    A constraint limits the available solution options (e.g., budget, regulation, existing technology), while a requirement defines what the solution must do or be.

  6. When should a BA formally re-baseline requirements?

    Answer: After approved changes accumulate enough impact to warrant a new controlled baseline

    Re-baselining is warranted when approved changes are substantial enough that the original baseline no longer accurately represents the agreed scope.

  7. A BA is preparing the requirements package for handoff to the development team. Which element is MOST critical to include for each requirement to ensure testability?

    Answer: Measurable acceptance criteria that define the conditions for satisfaction

    Acceptance criteria provide the objective, measurable conditions under which a requirement is considered satisfied, enabling testers to verify the solution.

How this page was made: written with AI tools and published by Nathan Beja, founder of Practice Test Geeks, who is responsible for its content. Exam facts are checked against the official sources listed below. Not reviewed by a subject-matter expert. Editorial policy

Sources & references

Exam facts on this page (fees, format, dates, passing scores) are checked against these official sources; the date is our last check. Editorial policy

  1. iiba.org — Eligibility, retake policy, score release, test delivery, fees, exam format, time limit, score validity, renewal, passing score · verified Oct 2026