What is 'bid leveling' in the subcontractor selection process?
Select your answer
A
Requiring all subcontractors to submit bids on identical forms
B
Adjusting received bids to a common scope basis so they can be fairly compared
C
Averaging all received bids to establish the contract price
D
Eliminating the highest and lowest bids before selection