Estimating and Cost Control Flashcards

7 cards from real CBP practice questions. Tap to flip, then mark Knew It or Still Learning — missed cards come back until you master them.

Read the first 7 Estimating and Cost Control flashcards as text
  1. At which stage of a project is a square-foot (cost-per-square-foot) estimate most appropriate?

    Answer: Early conceptual budgeting before plans are complete

    Square-foot estimates use historical averages and are best for quick early budgets, not detailed bids.

  2. A builder's total project cost is $200,000 and the company wants a 20% gross margin on the selling price. What should the selling price be?

    Answer: $250,000

    Selling price = cost / (1 - margin) = $200,000 / 0.80 = $250,000.

  3. A 25% markup on cost is equivalent to what gross margin on the selling price?

    Answer: 20%

    Margin = markup / (1 + markup) = 0.25 / 1.25 = 20%.

  4. An estimator measures 1,000 square feet of floor tile and applies a 10% waste factor. How many square feet should be ordered?

    Answer: 1,100 sq ft

    1,000 sq ft x 1.10 = 1,100 sq ft to cover cuts, breakage, and waste.

  5. Which item is typically classified as a job-site indirect cost (general conditions) rather than a direct construction cost?

    Answer: Portable toilet rental for the site

    General conditions such as temporary facilities support the job but are not built into the finished structure.

  6. What is the primary purpose of a contingency line in a construction estimate?

    Answer: To cover unforeseen costs within the defined scope

    Contingency covers unknowns and estimating risk within the scope; owner changes are handled by change orders.

  7. A unit-price estimate is calculated primarily by:

    Answer: Multiplying measured quantities of each work item by a cost per unit

    Unit-price estimating multiplies takeoff quantities (CY, SF, LF, each) by known unit costs.

How this page was made: written with AI tools and published by Nathan Beja, founder of Practice Test Geeks, who is responsible for its content. Exam facts are checked against the official sources listed below. Not reviewed by a subject-matter expert. Editorial policy

Sources & references

Exam facts on this page (fees, format, dates, passing scores) are checked against these official sources; the date is our last check. Editorial policy

  1. portal.ct.gov — Eligibility · verified Oct 2026
  2. phta.org — Score validity, test delivery, exam dates, registration deadline, score release, test dates, fees, exam format, passing score, time limit · verified Oct 2026
Estimating and Cost Control Flashcards — CBP Study Cards with Answers