Construction Planning and Management Flashcards

7 cards from real CBP practice questions. Tap to flip, then mark Knew It or Still Learning — missed cards come back until you master them.

Read the first 7 Construction Planning and Management flashcards as text
  1. In a Critical Path Method (CPM) schedule, what is total float?

    Answer: The time an activity can be delayed without delaying project completion

    Total float is the amount of time an activity can slip without pushing back the project finish date.

  2. An activity has an early start of day 10, a duration of 5 days, and a late finish of day 18. What is its total float?

    Answer: 3 days

    Early finish is day 15, so total float equals late finish 18 minus early finish 15, which is 3 days.

  3. What does free float represent in a CPM network?

    Answer: Delay allowed without affecting the early start of any following activity

    Free float is the slack an activity has before it delays the early start of its immediate successor.

  4. Which dependency type describes drywall hanging that cannot start until framing inspection is approved?

    Answer: Finish-to-start

    The successor (drywall) can only start after the predecessor (inspection) finishes, which is a finish-to-start relationship.

  5. A builder overlaps trades so interior painting starts on the first floor while drywall finishing continues upstairs. What is this schedule compression technique called?

    Answer: Fast-tracking

    Fast-tracking performs sequential activities in parallel to shorten duration, usually at increased risk of rework.

  6. Adding a second framing crew to shorten the framing phase at higher cost is an example of what?

    Answer: Crashing

    Crashing shortens activity duration by adding resources, which typically increases direct cost.

  7. What is the primary purpose of a three-week look-ahead schedule on a home building project?

    Answer: To coordinate near-term trade work, materials, and inspections in detail

    Look-ahead schedules break the master schedule into detailed short-term tasks so superintendents can line up crews, deliveries, and inspections.

How this page was made: written with AI tools and published by Nathan Beja, founder of Practice Test Geeks, who is responsible for its content. Exam facts are checked against the official sources listed below. Not reviewed by a subject-matter expert. Editorial policy

Sources & references

Exam facts on this page (fees, format, dates, passing scores) are checked against these official sources; the date is our last check. Editorial policy

  1. portal.ct.gov — Eligibility · verified Oct 2026
  2. phta.org — Score validity, test delivery, exam dates, registration deadline, score release, test dates, fees, exam format, passing score, time limit · verified Oct 2026