You have a recurring tendency to underestimate task durations. Which planning strategy would most effectively correct this?
-
A
Avoid making time estimates altogether
-
B
Track actual vs. estimated time on past tasks and use that data to calibrate future estimates
-
C
Always double your first estimate as a rule of thumb
-
D
Assign all time-sensitive tasks to someone else