PERT (Program Evaluation and Review Technique) uses three time estimates for each activity. What are they?
-
A
Optimistic, most likely, and pessimistic
-
B
Minimum, average, and maximum cost
-
C
Early start, late start, and target start
-
D
Best case, base case, and contingency