CAC Construction Scheduling and Planning 2 — Questions and Answers
Question 1: PERT (Program Evaluation and Review Technique) uses three time estimates for each activity. What are they?
- Optimistic, most likely, and pessimistic (Correct answer)
- Minimum, average, and maximum cost
- Early start, late start, and target start
- Best case, base case, and contingency
Correct answer: Optimistic, most likely, and pessimistic
PERT uses optimistic (O), most likely (M), and pessimistic (P) durations to calculate a weighted average expected time for each activity.
Question 2: A Finish-to-Finish (FF) relationship with a lag of 5 days means:
- The successor must finish at least 5 days after the predecessor finishes (Correct answer)
- The successor must start 5 days after the predecessor finishes
- Both activities must finish within 5 days of each other
- The predecessor must finish 5 days before the successor starts
Correct answer: The successor must finish at least 5 days after the predecessor finishes
A Finish-to-Finish relationship with a positive lag requires the successor to finish a specified number of days after the predecessor finishes.
Question 3: Which document serves as the baseline against which schedule progress is measured throughout a project?
- The approved project schedule baseline (Correct answer)
- The bid schedule submitted at procurement
- The contractor's preliminary schedule
- The owner's milestone list
Correct answer: The approved project schedule baseline
The approved schedule baseline is the frozen snapshot of the original plan used to measure deviations and report schedule performance.
Question 4: What is 'fast-tracking' in construction project scheduling?
- Overlapping phases or activities that would normally be done sequentially (Correct answer)
- Accelerating a schedule by adding more resources to critical activities
- Removing non-critical activities from the schedule
- Substituting faster construction methods for original methods
Correct answer: Overlapping phases or activities that would normally be done sequentially
Fast-tracking compresses the schedule by performing phases in parallel rather than sequentially, though it often increases risk and coordination demands.
Question 5: Which scheduling method assigns probability distributions to activity durations to model schedule risk?
- Monte Carlo simulation (Correct answer)
- Precedence Diagramming Method (PDM)
- Arrow Diagramming Method (ADM)
- Linear Scheduling Method (LSM)
Correct answer: Monte Carlo simulation
Monte Carlo simulation runs thousands of iterations using probability distributions for activity durations to produce a probabilistic project completion date.
Question 6: In a Precedence Diagramming Method (PDM) network, activities are represented by:
- Nodes (boxes), with arrows showing dependencies (Correct answer)
- Arrows, with nodes representing events
- Horizontal bars on a time scale
- Diagonal lines showing production rates
Correct answer: Nodes (boxes), with arrows showing dependencies
PDM (also called Activity-on-Node) places activities in boxes connected by arrows that define the logical relationships between them.
Question 7: What is the purpose of a 3-week lookahead schedule on a construction project?
- To identify and remove near-term constraints so field crews can execute work without interruption (Correct answer)
- To provide the owner with a monthly progress report
- To replace the master CPM schedule for day-to-day use
- To satisfy the contract requirement for weekly schedule updates
Correct answer: To identify and remove near-term constraints so field crews can execute work without interruption
A 3-week lookahead is a short-interval schedule used to identify and resolve upcoming constraints such as material deliveries, inspections, and labor needs.
PERT (Program Evaluation and Review Technique) uses three time estimates for each activity.
What are they?