  1. A process is said to be in a state of statistical control when:

    Answer: Only common cause variation is present

    Statistical control means the process exhibits only common cause (natural, random) variation with no special causes present.

  2. Which DMAIC phase focuses on identifying and validating the root cause of a problem?

    Answer: Analyze

    The Analyze phase uses data and tools like fishbone diagrams and hypothesis testing to identify and validate root causes.

  3. A Pareto chart is based on which principle?

    Answer: Roughly 80% of problems stem from 20% of causes

    The Pareto principle (80/20 rule) states that approximately 80% of effects come from 20% of causes, helping prioritize improvement efforts.

  4. What does a process capability index (Cpk) measure?

    Answer: How centered and capable a process is relative to its specification limits

    Cpk accounts for both the spread and the centering of a process relative to the specification limits.

  5. In a fishbone (Ishikawa) diagram, the 'bones' typically represent:

    Answer: Major categories of potential causes

    The branches (bones) of an Ishikawa diagram represent major cause categories such as Man, Machine, Method, Material, Measurement, and Environment.

  6. Which type of control chart is most appropriate for monitoring the proportion of defective items in a process?

    Answer: p chart

    The p chart monitors the proportion (fraction) of nonconforming units in samples of varying or constant size.

  7. The primary goal of a process improvement team's charter is to:

    Answer: Define the scope, objectives, and boundaries of the improvement project

    A project charter aligns the team by clearly defining the problem statement, goals, scope, timeline, and team roles before work begins.

How this page was made: written with AI tools. Exam facts are checked against the official sources listed below. Not reviewed by a subject-matter expert. Editorial policy

Sources & references

Exam facts on this page (fees, format, dates, passing scores) are checked against these official sources; the date is our last check. Editorial policy

  1. asq.org — Eligibility, fees, exam format, registration deadline, retake fee, test dates, score release, test delivery, score validity, passing score · verified Oct 2026