A product owner notices that a key stakeholder consistently misses sprint reviews. What is the BEST first action?
-
A
Cancel future reviews until attendance improves
-
B
Understand why the stakeholder is absent and adjust the format or timing
-
C
Proceed without the stakeholder and send written summaries
-
D
Escalate to senior management immediately