Question 1: A product owner notices that a key stakeholder consistently misses sprint reviews. What is the BEST first action?
- Cancel future reviews until attendance improves
- Understand why the stakeholder is absent and adjust the format or timing (Correct answer)
- Proceed without the stakeholder and send written summaries
- Escalate to senior management immediately
Correct answer: Understand why the stakeholder is absent and adjust the format or timing
Understanding the root cause of absence allows the team to adapt the engagement approach and re-establish meaningful participation.
Question 2: In agile business analysis, a 'silent stakeholder' is BEST described as someone who:
- Has no interest in the project outcome
- Holds influence but rarely voices opinions in group settings (Correct answer)
- Has been formally excluded from decision-making
- Only reviews deliverables at project close
Correct answer: Holds influence but rarely voices opinions in group settings
Silent stakeholders can significantly impact a project despite low visible engagement, so BAs must proactively draw out their perspectives.
Question 3: Which technique BEST helps a business analyst identify hidden stakeholder concerns during requirements elicitation?
- Sending a detailed questionnaire by email
- Conducting one-on-one interviews with open-ended questions (Correct answer)
- Reviewing the project charter only
- Holding a single large group workshop
Correct answer: Conducting one-on-one interviews with open-ended questions
One-on-one interviews create a safe environment where stakeholders are more likely to share concerns they wouldn't raise in group settings.
Question 4: A stakeholder requests a feature that conflicts with the product vision. How should an agile business analyst respond?
- Add it to the backlog without question
- Reject the request outright
- Facilitate a conversation to understand the underlying need and explore alternatives (Correct answer)
- Defer the decision to the development team
Correct answer: Facilitate a conversation to understand the underlying need and explore alternatives
Understanding the underlying need often reveals solutions that satisfy the stakeholder without compromising product vision.
Question 5: What is the PRIMARY purpose of a stakeholder communication plan in an agile project?
- To document every conversation with stakeholders
- To ensure each stakeholder receives relevant information in a format and cadence that meets their needs (Correct answer)
- To restrict access to sensitive project data
- To replace regular sprint ceremonies
Correct answer: To ensure each stakeholder receives relevant information in a format and cadence that meets their needs
A communication plan tailors information delivery to stakeholder needs, improving engagement and reducing misunderstandings.
Question 6: During a sprint, a stakeholder directly asks a developer to add a feature outside the sprint backlog. What should the developer do?
- Implement the feature immediately to keep the stakeholder happy
- Ignore the request and focus on the sprint backlog
- Redirect the stakeholder to the product owner and explain the backlog process (Correct answer)
- Escalate to the scrum master to reprimand the stakeholder
Correct answer: Redirect the stakeholder to the product owner and explain the backlog process
Directing stakeholders to the product owner protects the sprint commitment while ensuring the request is properly evaluated.
Question 7: Which agile principle MOST directly supports continuous stakeholder collaboration?
- Deliver working software frequently
- Business people and developers must work together daily throughout the project (Correct answer)
- Simplicity is essential
- The best architectures emerge from self-organizing teams
Correct answer: Business people and developers must work together daily throughout the project
The Agile Manifesto explicitly calls for daily collaboration between business people and developers to ensure alignment.
A product owner notices that a key stakeholder consistently misses sprint reviews.
What is the BEST first action?