A business analyst is facilitating a sprint review. A stakeholder requests a major feature change mid-sprint. What is the BEST response?
-
A
Pause the sprint and incorporate the change immediately
-
B
Log the request in the product backlog for prioritization by the product owner
-
C
Reject the request since it was not in the original sprint plan
-
D
Escalate the request to senior management for approval