Your team is asked to deliver a project with an unrealistic deadline. What is the most effective team response?
-
A
Agree to the deadline and work excessive hours silently
-
B
Collectively communicate risks and propose an adjusted timeline or reduced scope to stakeholders
-
C
Refuse to start the project
-
D
Have one person secretly negotiate without consulting the team